Apartment renovation mistakes that cost twice

Most expensive renovation mistakes are not about bad workmanship. They are about the wrong order, the wrong assumptions or the wrong quote.

Author / technical lead: Bauman Raymond Attila · Last reviewed: 05/11/2026

Plastered room with steel props
In short

The costliest apartment renovation mistakes are doing finishes before services, accepting a vague lump-sum quote, assuming a wall can go without checking, closing walls before testing pipes and electrics, ignoring the community of owners and choosing finishes that do not suit the use of the flat. Each is avoidable with a clear sequence, an itemised quote and checks before anything is covered.

Mistake 1: Why is doing the finishes before the services so costly?

The most common and most expensive mistake. A new kitchen goes in, the walls are painted, the floor is laid — and then the electrics fail an inspection or the old pipes start leaking. Everything that covers them has to be broken and redone. In an older flat, decide on the services first, even if you plan to renovate in phases. Our services guide explains how to judge their condition.

Mistake 2: Why is a vague quote a problem?

A quote that says “bathroom renovation” with a single figure tells you nothing about what is included. Does it cover new waste pipes? Waterproofing? Who buys the tiles? When something is not included, it becomes an extra. An itemised quote, with every task, unit and quantity on its own line, is the best protection against surprises and the only way to compare contractors fairly.

Mistake 3: Assuming a wall can come down

Owners often plan an open-plan kitchen around a wall that turns out to be structural, or a bathroom move that the waste cannot support. Check before committing: drawings, a technician’s view for anything doubtful, and an on-site check of waste levels. Our layout guide explains what to verify.

Mistake 4: Covering up without testing

Once tiles and plaster go on, nobody can see the pipes or cables. Pressure-testing the water supply, checking waste connections and having the electrical installation verified by the authorised partner installer before closing walls takes little time and avoids the worst kind of problem: the one found after handover, behind new finishes, sometimes in the neighbour’s ceiling.

Mistake 5: Forgetting the building

Starting works without informing the community’s representative, ignoring rules on working hours, blocking the lift with materials or leaving debris on the landing creates conflict fast. The horizontal property law requires owners to inform the community before works, and shared elements need its agreement. A short note to the administrator and good site manners prevent most problems.

Mistake 6: Choosing finishes for photos rather than use

A finish that looks perfect in a showroom may be wrong for a rental flat, a home with pets or a bathroom without good ventilation. Think about cleaning, wear, humidity and repair. For flats near the sea, consider how metal fittings and exposed fixings cope with a salty atmosphere, and ask for materials suited to that environment.

Mistake 7: Splitting the job between uncoordinated trades

Hiring the plumber, the electrician, the tiler and the painter separately can work if you are prepared to coordinate them. Often, nobody does, and each blames the others for delays and defects. With one contractor coordinating everything, there is one sequence and one person responsible. See our full apartment renovation page for how that works in practice.

Mistake 8: Leaving decisions until the last minute

Choosing tiles, taps or kitchen units while the trades are waiting creates delays and rushed choices. Some items need ordering in advance, and late decisions can disrupt the whole sequence. Make the main choices before work starts, keep a simple list of what is decided and what is still open, and know which decisions are needed by which stage. On our jobs we tell you in advance what we need from you and when, so nothing stops the site. If you are abroad, it helps to have samples or photos of the options sent to you early, so the decision is made calmly rather than over a hurried phone call while the tiler waits. The same applies to small items that are easy to forget, such as door handles, light fittings and the position of the television point.

Mistake 9: Not keeping records

Owners who do not keep the quote, invoices, certificates and photos of the hidden services regret it later: when selling, when letting, when a leak appears or when a new electricity contract needs the certificate. Ask your contractor for photos of pipe and cable routes before walls are closed, labelled by room so they are easy to find years later, and keep them with the property documents together with the electrical installation certificate issued by the authorised partner installer where the work required one.

Author / technical lead

Bauman Raymond Attila · Reforma Pisos Málaga · Avenida Antonio Belón 3, Marbella. Last reviewed: 05/11/2026.

FAQ

Frequently asked questions

What is the single biggest renovation mistake?

Doing finishes before deciding on the services.

How detailed should a quote be?

Every task on its own line, with unit, quantity and what is included or excluded.

Should pipes be tested before tiling?

Yes, always. A leak found after tiling costs far more than the test.

Can I trust that a wall is a partition?

Not by appearance alone. Check drawings or get a technician’s view if in doubt.

Do I need to tell the community?

Yes, the law requires you to inform its representative before works.

Is it a mistake to renovate in phases?

Not if the phases are planned so no work is undone later.

Are cheap materials always a mistake?

No. The mistake is choosing materials unsuited to how the flat is used.

Should I hire trades separately to save money?

Only if you are ready to coordinate them yourself and accept the risk of gaps.

What if I find a mistake after handover?

Contact the contractor promptly. Our work is covered by a guarantee, with terms in the quote.

How do you avoid these mistakes?

With a fixed sequence, itemised quotes and checks before anything is covered.

Free, itemised quote

Send us photos and the approximate floor area

A few photos and a rough square-metre figure are enough for a first assessment. If it suits you, we then visit the property and prepare an itemised quote, line by line.

  • One contractor, one point of contact
  • Itemised quote with no vague lump sums
  • Materials purchasing and final clean handled by us
  • Work carried out with a guarantee and public liability insurance
Will anyone live there during the works?